Seven stages, one site manager, no surprises.

An extension usually takes six to nine months from first visit to handover, and three to five of those are on site. Click through each stage to see what happens, who's involved, how long it takes and when money changes hands.

When you pay

Stage payments that follow the work, never lead it.

Example schedule for a £120,000 rear extension. Every payment is invoiced only after your site manager has walked you round the finished stage.

Example payment schedule
StageInvoiced whenShareExample amount
DepositContract signed, start date booked5%£6,000
GroundworksFoundations and slab passed by building control15%£18,000
ShellWalls to wall-plate, steels in and signed off20%£24,000
WeathertightRoof, rooflights and glazing installed20%£24,000
First fix & plasterServices in, walls plastered15%£18,000
Practical completionKitchen, floors, second fix; completion certificate issued22.5%£27,000
RetentionReleased after the snagging visit (3 months)2.5%£3,000

Example pricing for demonstration. Payment terms here are illustrative, not contract wording.

Client progress portal

Your build, updated every Friday.

A look around a demo portal for a fictional job. Real clients get a private link at contract signing; nothing here is connected to a live system.

Demo project · Elmfield Road, N10Rear kitchen extension
Week 9 of 16 · on programme
  1. Blockwork and brick walls rising for the rear extension
    Fri 3 Oct · week 9 · Danny

    Walls to wall-plate

    Blockwork to wall-plate height on both sides, facing brick matched to the house. Steels go in Tuesday; building control inspection booked Wednesday 10am.

  2. Steel beams installed across the opened back of the house
    Fri 26 Sep · week 8 · Danny

    Back of the house opened

    Rear wall removed under props, two steels in on padstones. The engineer visited and signed off the bearings. Dust screen moved forward to the hallway.

  3. Scaffold around a part-built extension at the back of a semi-detached house
    Fri 12 Sep · week 6 · Danny

    Scaffold up, upper works started

    Scaffold erected for the parapet and the bathroom window above. Neighbours on both sides given the schedule for the noisy days.

  4. Nearly finished extension with blockwork, new glazed doors and the garden being cleared
    Preview · week 12 · planned

    Glazing and roof

    Slider and rooflights arrive week 11. You'll be weathertight by the end of week 12, ahead of the first frost.